Time schedule
Preparatory phase
- january 2007 – april 2009: preparation of project and construction
documentation
- 30.4.2009: submission of the project application
- 1.5.2009 – 24.11.2009: approval process
- 10.9.2009: finalization of area management
- 23.11.2009: building permit
- 24.11.2009: Decision on the award of the grant number 0017/01/01
from RDIOP
Implementation phase
- 1.1.2010: start of the project implementation
- October 2010: start of construction works
- Ocotber 2011: opening of reconstructed biosignal laboratories
- July 2012: opening of rebuilt magnetic resonance laboratories
- October 2012: opening of new laboratories of advanced technologies
- 31.12.2013: the end of the project implementation
Operational phase
- 2013 – 2018: minimal sustainability period of project outputs