Time schedule

Preparatory phase

  • january 2007 – april 2009: preparation of project and construction documentation
  • 30.4.2009: submission of the project application
  • 1.5.2009 – 24.11.2009: approval process
  • 10.9.2009: finalization of area management
  • 23.11.2009: building permit
  • 24.11.2009: Decision on the award of the grant number 0017/01/01 from RDIOP

Implementation phase

  • 1.1.2010: start of the project implementation
  • October 2010: start of construction works
  • Ocotber 2011: opening of reconstructed biosignal laboratories
  • July 2012: opening of rebuilt magnetic resonance laboratories
  • October 2012: opening of new laboratories of advanced technologies
  • 31.12.2013: the end of the project implementation

Operational phase

  • 2013 – 2018: minimal sustainability period of project outputs